Prompt payment is more than a contract management issue for businesses bidding for major government work. Buyers may examine how reliably suppliers pay their own supply chains as part of the procurement process, particularly when the delivery model depends on subcontractors.

For bidders, the challenge is to understand which requirements apply, gather accurate payment data and show that the business can meet its obligations throughout delivery. Two relevant policies are PPN 018, which concerns suppliers’ payment approaches at procurement stage, and PPN 021, which addresses payment spot checks during applicable public contracts.

Why prompt payment matters in a public tender

Late payment can affect subcontractor cashflow, weaken supply chains and create delivery risk. A buyer commissioning a long-term works or services contract needs confidence that its lead supplier will manage the businesses supporting delivery responsibly.

That is why prompt payment evidence can form part of a supplier’s conditions of participation for major contracts. It should be addressed early by finance and procurement colleagues, not left until the final quality review or treated as a general social value statement.

Desk calendar date circled

PPN 018: When does the procurement-stage requirement apply?

PPN 018 applies to relevant procurements advertised from 1 October 2025 by central government departments, their executive agencies and non-departmental public bodies. It addresses goods, services and works public contracts other than special regime contracts, where the anticipated value exceeds £5 million including VAT per year and the measure is relevant and proportionate.

Other public sector authorities may choose to use the approach, but suppliers should not assume that every NHS, local government or devolved procurement applies the same PPN. The tender notice and participation documents determine what the buyer requires for the particular opportunity.

What payment performance must suppliers demonstrate?

Under the current PPN 018 approach, relevant bidders generally need to demonstrate that they pay at least 95% of invoices within 60 days, or at least 90% with an acceptable action plan, and that their average invoice payment time is 45 days or fewer. The required metrics must be met together in at least one of the two previous six-month reporting periods, alongside the applicable questions about paying invoices within agreed terms.

Measure

Current requirement

What to check

Invoices paid within 60 days

At least 95%, or 90% with a compliant action plan

Performance for the relevant reporting period

Average payment time

45 days or fewer

Calculated across the same reporting period

Payment within agreed terms

Demonstrate compliance or provide the explanation required by the questions

Systems, records and reasons for exceptions

Reporting evidence

Normally the two most recent six-month periods, subject to the guidance

Published payment practice reports or equivalent data

The current average payment threshold replaced the previous 55-day standard from 1 October 2025. The PPN 018 assessment guidance also explains the treatment of new entrants, intercompany payments, action plans and alternative evidence. Those details matter if a supplier is close to a threshold or has limited reporting history.

Auditor reviewing documents

What documents should a bid team assemble?

Begin with the questions in the current tender pack. Finance colleagues should confirm how each metric has been calculated, which legal entity it covers and whether the reporting period matches the buyer’s requirements.

  • Published payment practices reports where the business is required to report them.
  • Equivalent payment performance data for smaller businesses that do not publish statutory reports.
  • Written payment policies, procedures and records showing how invoices are processed.
  • Evidence explaining late payments or disputed invoices, where relevant.
  • A measurable improvement plan where the PPN permits one and the required performance level has not been met.

A response should be traceable back to reliable business records. Avoid copying headline payment percentages into a tender without checking the calculations, because a buyer may verify them before award.

PPN 021: payment spot checks during contract delivery

PPN 021 is related but distinct. It sets out how in-scope central government bodies can carry out checks to test whether subcontractors are being paid in line with the 30-day payment requirements under section 73 of the Procurement Act 2023.

From 1 October 2025, it applies to relevant new central government public contracts with a value above £5 million including VAT per year, subject to the policy’s exclusions and scope. Payment spot checks should generally take place at least once every six months, with a different frequency permitted in certain circumstances under the guidance.

This makes good invoice data and clear subcontracting arrangements important beyond the tender submission. Lead contractors should be able to show how they cascade appropriate terms, handle valid and undisputed invoices and monitor compliance throughout their delivery chain.

How do the 30-day subcontract payment terms work?

Under section 73, qualifying public subcontracts have 30-day payment terms implied into them, even if their written terms omit or attempt to override those requirements. The focus is on paying valid, undisputed invoices promptly; the wider statutory application and exclusions should be checked against the relevant contract.

Suppliers should review subcontract templates and accounts payable processes before bidding. It is easier to address a gap in approval workflows or payment reporting now than to discover that the business cannot evidence compliance after a contract has been awarded.

Team working together

Practical preparation for suppliers

The strongest approach is to treat prompt payment as a joint finance, commercial and bid-management responsibility. The bid team needs accurate evidence, finance needs to own the metrics, and procurement or operations needs to ensure the delivery model can sustain the required payment practices.

Action

Owner

Reason

Check whether PPN 018 applies

Bid manager

Confirm scope and current participation questions

Validate payment data

Finance

Avoid inconsistent or unverified figures

Review subcontract terms

Commercial/legal team

Prepare for section 73 requirements and checks

Document improvement actions

Finance and operations

Demonstrate how performance is being improved where permitted

These actions should sit alongside the other requirements in your Procurement Specific Questionnaire preparation. Prompt payment data is not a substitute for a strong technical submission, but a failure on a mandatory participation requirement can undermine even an otherwise competitive bid.

What if your payment performance falls below the threshold?

Suppliers should not assume that an action plan can resolve every performance gap. PPN 018 allows a compliant action plan to support the 90% to 95% range for invoices paid within 60 days in specified circumstances, but the 45-day average payment test remains important. The guidance also sets out special treatment for eligible new entrants and some other circumstances.

If the business is below the required level, first validate the underlying figures and reporting periods, then examine whether the tender's particular rules offer an applicable route to demonstrate compliance. An improvement plan should identify owners, timescales and measurable actions, not just state an intention to pay suppliers more quickly.

Contract payment information

How to explain payment processes in your tender

Where the buyer asks about payment systems, give a straightforward account of how an invoice is received, approved, disputed if necessary and paid. Explain the controls that prevent invoices becoming stuck between departments, and provide the specific data the questionnaire requests rather than a general claim that your business values suppliers.

For a contract involving substantial subcontracting, link the account to the proposed delivery arrangements. Buyers are looking for credible evidence that the supply chain will remain stable during performance, which depends on effective day-to-day processes as much as on a published policy.

How Thornton & Lowe can help

Our bid writing specialists help suppliers interpret participation requirements, coordinate evidence and prepare quality responses for major public sector tenders. Where payment performance requirements apply, we can help structure the submission and identify missing information for your finance and commercial teams to address.

Getting the evidence organised early helps avoid late compliance surprises and allows the bid team to concentrate on demonstrating value to the buyer. The right approach will always depend on the specific procurement documents and the supplier’s actual delivery arrangements.